Minsk Arena, Minsk, Belarus

minsk-arena-vimarkThe design of the new winter sports area of Minsk, capital of Belarus, is a multifunctional centre, unique in Europe.

Officially inaugurated on 30th January 2010, the Minsk Arena can hold 15,000 spectators.
There is also a skating stadium and a veldome with a further 5000 seats.

One of the primary uses of the facility is ice hockey, as the building is the home rink of HC Dinamo Minsk and primarily is used for hockey games, figure skating, short-track speed skating and other sports on ice, but is also used for the organization of concerts and other mass performances.

With 3 restaurants, 7 coffee shops, and numerous VIP lounges offering services and comforts for guests.

The following data describes the uniqueness and the size of the project:

minsk-arena-vimark-03
THE PROJECT

Stadium
Ice rink: 11517 m2
Spectators: 3000
Volume: 285.000 m3
Arena
Ice rink: 1860 m2
Spectators: 15.0086

COOLING SYSTEM

Stadium
Pipe line: 140 km
Air conditioning units: 16
Arena
Pipe line: 25 km
Air conditioning units: 36

MAIN REFRIGORATOR

Ice refrigeration: 4000 kW, 4 compressors
Refrigeration for air conditioning: 6000 kW, 3 compressors
Electric motors: 7 of 710 kW to 10000 Volt

FLOORING

Stadium
Cls RCK 35-55: 1.896,4 m3
Synthetic fibres: 5.700 kg
Welded mesh: 83.077 kg
Arena
Cls RCK 35-55: 308,80 m3
Synthetic fibres: 950 kg
Welded mesh: 12.587 kg

INDUSTRIAL FLOORING

Quazocem: 13.262 kg
Seasoning additive: 5.500 litres
Nylon for seasoning: 14.588,20 m

 